  "id": "c7890def-1234-5678-abcd-ef0123456789",
  "containerId": "b5623fe1-4e59-4d33-a928-f1234abc5678",
  "displayId": 142,
  "title": "Rebar spacing does not match structural drawings",
  "description": "Rebar spacing in the east abutment footing is 18 inches OC, but structural drawings specify 12 inches OC. Requires corrective action before concrete pour scheduled for next week.",
  "status": "open",
  "issueTypeId": "type-quality-001",
  "issueSubtypeId": "subtype-structural-001",
  "dueDate": "2026-04-25",
  "startDate": "2026-04-19",
  "locationId": "loc-east-abutment-001",
  "locationDescription": "East Abutment Footing - Grid Line E5",
  "assignedToId": "user-engineer-jsmith-001",
  "assignedToType": "user",
  "createdBy": "user-inspector-bdoe-002",
  "createdAt": "2026-04-19T08:15:00Z",
  "updatedAt": "2026-04-19T08:15:00Z",
  "closedBy": null,
  "closedAt": null,
  "commentCount": 2,
  "attachmentCount": 3,
  "linkedDocuments": [
    {
      "urn": "urn:adsk.wipprod:fs.file:vf.abc123def456"
    }
  ]
}